PROCUREMENT INTELLIGENCE

Equipment Lead Times

Updated monthly via primary research with equipment buyers, manufacturer reps, and procurement leads

Transformers (115kV+)
72wks
+18% YTD
Medium-Voltage Switchgear
52wks
+3% YTD
Liquid Cooling Systems
46wks
+28% YTD
Backup Generators (2MW+)
22wks
-8% YTD
UPS Systems (500kVA+)
18wks
0% YTD
Transformers (115kV+)
12-month lead time trend
72 wks
+18% since Jan 2024
Critical lead time — order now for H1 2027 delivery. Most manufacturers allocated through end of 2026.
By Manufacturer
ABB68 wks
Allocated through Q4 2026
Siemens76 wks
New orders Q1 2027 delivery
Hitachi Energy72 wks
US plant at full capacity
ELSCO (refurb)24 wks
Limited availability
PROCUREMENT INTELLIGENCE
Primary research data sourced from 6–8 equipment buyers and manufacturer reps per cycle. Updated on the first business day of each month. Contact an Expert for a live procurement call.
Lead Time Urgency Guide
Low — order as normal
0–19 weeks
Moderate — start procurement planning
20–35 weeks
High — order immediately
36–59 weeks
Critical — sourcing alternatives needed
60+ weeks